✓ Cloud synced 6:41 DR

Site Dashboard

Mon, Jul 6 · 06:45 — morning briefing
Crews active 6 45 workers on site
Overlays live 4 Rev C4 (Structural) current
Open QC items 9 ⚠ 3 pending review
Glasses online 11/12 #03 charging — 18%
ℹ Insight
Sequence deviation risk — MEP Rough-In ahead of L3 slab pour sign-off (Rev C4) 06:32 · MEP Rough-In · L3 North
Review →
⚠ Rework risk
Curtain wall anchors installed against Rev C3 — Rev C4 changed torque spec 06:18 · Curtain Wall Crew · L1 South
View torque spec →

Today's crews

View all 6 crews →
CrewZoneAssigned overlayProgressCrew size
Framing Crew B L2 East L2 wall framing (Rev C4) 62% 8
MEP Rough-In L3 North L3 conduit routing (Rev C4) 45% 6
Curtain Wall Crew L1 South Anchor layout⚠ Rev C3 — outdated 78% 7
Rebar Crew A L3 slab L3 slab rebar spacing (Rev C4) 30% 9

QC due today

5
Open Quality Control →
L3 slab rebar spacing Rebar Crew A · L3 slab · due 10:00
⚠ Pending
Curtain wall anchor torque Curtain Wall Crew · L1 South · re-test required
✕ Failed
L2 stud spacing verification Framing Crew B · L2 East · photo attached
✓ Passed
L3 conduit clearance @ beam B-14 MEP Rough-In · L3 North · due 14:00
⚠ Pending
L2 fire-stop penetrations Framing Crew B · L2 West · due 16:00
⚠ Pending
Site weather — Ottawa
−2°C Overcast · wind 24 km/h NW
⚠ Crane advisory — gusts to 38 km/h after 13:00

Sync activity

Glasses #07 synced Rev C4 6:41 · battery 82%
Rev C4 (Structural) — from Revit 6:12 · 214 elements changed
Overlay published: L2 wall framing → Framing Crew B 6:05
Glasses #03 low battery — moved to charger 5:58 · 18%
Augvator Rideau Mixed-Use Tower — Ph. 2 ✓ 6:41

Site Dashboard

Mon, Jul 6 · 06:45

AI Alerts

All →
ℹ Insight Sequence deviation risk — MEP Rough-In ahead of L3 slab pour sign-off (Rev C4)
06:32 · L3 North Review →
⚠ Rework risk Curtain wall anchors installed against Rev C3 — Rev C4 changed torque spec
06:18 · L1 South View spec →

QC due today

5
All →
L3 slab rebar spacing Rebar Crew A · due 10:00
⚠ Pending
Curtain wall anchor torque Curtain Wall Crew · re-test
✕ Failed
L2 stud spacing verification Framing Crew B · photo attached
✓ Passed
L3 conduit clearance @ B-14 MEP Rough-In · due 14:00
⚠ Pending
L2 fire-stop penetrations Framing Crew B · due 16:00
⚠ Pending

Today's crews

All 6 →
Framing Crew B 8 workers
L2 East · L2 wall framing (Rev C4)
62%
MEP Rough-In 6 workers
L3 North · L3 conduit routing (Rev C4)
45%
Curtain Wall Crew 7 workers
L1 South · Anchor layout ⚠ Rev C3
78%
Rebar Crew A 9 workers
L3 slab · L3 slab rebar spacing (Rev C4)
30%
Crews active 6 45 workers
Overlays live 4 Rev C4 current
Open QC items 9 ⚠ 3 pending
Glasses online 11/12 #03 charging
−2°C Overcast · wind 24 km/h NW
⚠ Crane advisory — gusts to 38 km/h after 13:00
✓ Cloud synced 6:41 DR

Projects

3 active · Mon, Jul 6
Rideau Mixed-Use Tower — Phase 2 Claridge Homes · Ottawa ON
Structure
54%
✓ Rev C4 synced 9 open QC · 6 crews · 45 workers
Kanata Logistics Hub Broccolini · Kanata ON
Envelope
71%
⚠ Rev pending 4 open QC · 4 crews · 28 workers
uOttawa Lab Retrofit University of Ottawa · Ottawa ON
Interiors
38%
✓ Rev A7 synced 2 open QC · 2 crews · 11 workers

Rideau Mixed-Use Tower — Phase 2

Claridge Homes · 6-storey mixed-use · Ottawa ON
Structure
Overall progress 54%

Milestones

Excavation & shoring ✓ Complete — Fri, Feb 13
Structure L1–L3 ✓ Complete — Fri, Jun 19
!
Structure L4–L6 ⚠ In progress — due Fri, Jul 10
Envelope Upcoming — starts Mon, Aug 3

Key dates

L3 slab pour sign-off Wed, Jul 8
Envelope start Mon, Aug 3
Substantial completion Fri, Feb 26, 2027

Team leads

DR
Daniel Roy Site Superintendent
PN
Priya Nair QC Lead
MT
Marc Tremblay BIM Coordinator

Linked BIM source

Revit — via Autodesk BIM 360 ✓ Synced
Rev C4 (Structural) — from Revit 6:12 · auto-sync every 30 min
Augvator Projects ✓ 6:41

Projects

3 active
Rideau Mixed-Use Tower — Phase 2 Claridge Homes
Structure
54%
✓ Rev C4 synced 9 QC · 6 crews
Kanata Logistics Hub Broccolini
Envelope
71%
⚠ Rev pending 4 QC · 4 crews
uOttawa Lab Retrofit University of Ottawa
Interiors
38%
✓ Rev A7 synced 2 QC · 2 crews
✓ Cloud synced 6:41 DR

Models & Overlays

Rev C4 (Structural) current · Mon, Jul 6

Model tree

Structural Rev C4
Architectural Rev A9
MEP Rev B9

Revision history — Structural

Rev C4 ✓ Current
From Revit — Mon, Jul 6 · 6:12 ℹ Changed: anchor torque spec, L4 beam sizes (214 elements)
Rev C3 From Revit — Tue, Jun 30 · 7:04
Superseded
Rev C2 From Revit — Mon, Jun 22 · 6:47
Superseded

3D preview

Rev C4 (Structural) — from Revit 6:12
⚠ 2 clashes
[ 3D model viewport — Rev C4 Structural · L1–L6 ]
⚠ Clash 1 — L4 beam B-07
⚠ Clash 2 — L4 conduit run

Publish to glasses

Framing Crew B 4 glasses
MEP Rough-In 3 glasses
Curtain Wall Crew 3 glasses
Georeference locked
Scale verified — 2 control points
2 clashes unresolved Review →
⚠ Resolve 2 clashes to enable publishing
Augvator Models & Overlays ✓ 6:41

Models & Overlays

Status & publish — full editing on desktop

Prepared overlay

⚠ 2 clashes
L2 wall framing — Rev C4 → Framing Crew B · L2 East · 4 glasses
⚠ Resolve 2 clashes on desktop to publish

Model revisions

Rev C4 — Structural ✓ Current
From Revit — Mon, Jul 6 · 6:12 ℹ Changed: anchor torque spec, L4 beam sizes
Rev B9 — MEP From Revit — Fri, Jul 3 · 16:20
✓ Synced
Rev C3 — Structural From Revit — Tue, Jun 30 · 7:04
Superseded

Active overlays

L2 wall framing (Rev C4) Framing Crew B · L2 East · 4 glasses
✓ Live
L3 conduit routing (Rev C4) MEP Rough-In · L3 North · 3 glasses
✓ Live
Anchor layout Curtain Wall Crew · L1 South · 3 glasses
⚠ Rev C3
✓ Cloud synced 6:41 DR

Tasks & Instructions

8 work packages · Mon, Jul 6
To assign 2
WP-221 L4 column formwork — grid B 9 AR steps · due Tue, Jul 7
WP-223 L2 fire-stop penetrations — west 6 AR steps · due 16:00
In progress 3
WP-214 L3 slab rebar placement Framing Crew B · 12 AR steps · due 15:00
7/12
WP-212 L3 conduit routing — north run MEP Rough-In · 8 AR steps · due 14:00
5/8
WP-209 L2 wall framing — east Framing Crew B · 10 AR steps · due Tue, Jul 7
6/10
Blocked 1
WP-219 Curtain wall anchors — L2 East Curtain Wall Crew · 7 AR steps ✕ Blocked Rev C4 torque spec change — awaiting updated instructions
Done 2
WP-205 L2 stud spacing verification Framing Crew B · done 6:20 ✓ Done
WP-201 L1 anchor layout — south facade Curtain Wall Crew · done Fri, Jul 3 ✓ Done
Augvator Rideau Mixed-Use Tower — Ph. 2 ✓ 6:41

Tasks

Mon, Jul 6
WP-214 · due 15:00 ℹ In progress
L3 slab rebar placement Framing Crew B · 12 AR steps
7/12
WP-219 ✕ Blocked
Curtain wall anchors — L2 East Rev C4 torque spec change — awaiting updated instructions
WP-221 · due Tue, Jul 7 To assign
L4 column formwork — grid B 9 AR steps
WP-205 · done 6:20 ✓ Done
L2 stud spacing verification Framing Crew B
✓ Cloud synced 6:41 DR

Quality Control

45 checkpoints · Mon, Jul 6
CheckpointZoneCrewEvidenceInsp.StatusTime
QC-078 L3 slab rebar spacing
L3 slab Rebar Crew A
2
DR ⚠ Pending 6:38
QC-079 Curtain wall anchor torque
L1 South Curtain Wall Crew
1
PN ✕ Failed 6:15
QC-074 L2 stud spacing verification
L2 East Framing Crew B
3
DR ✓ Passed 6:20
QC-072 L3 conduit clearance @ B-14
L3 North MEP Rough-In
1
PN ⚠ Pending 6:02
QC-070 L2 fire-stop penetrations
L2 West Framing Crew B ⚠ Pending
QC-068 L1 anchor embed plates
L1 South Curtain Wall Crew
2
DR ✓ Passed Jul 3
QC-078 · L3 slab · Rebar Crew A

L3 slab rebar spacing

⚠ Pending
[ evidence photo — glasses #07 · AR overlay visible ] 205 mm
Captured by J. Fortin · Glasses #07 · 6:38 · 2 photos
Spec 200 mm ±10
Measured 205 mm ✓ Within tolerance
Failing requires a note — a punch-list item is created automatically.

Punch list — failed items

2
PL-012 — Re-torque anchors, row 2 ✕ Open
From QC-079 · due Tue, Jul 7
PL-011 — Patch L2 fire-stop void, grid D ⚠ In review
From QC-066 · Framing Crew B · due today 16:00
Augvator Quality Control ✓ 6:41

Quality Control

9 pending · 2 failed · Mon, Jul 6
QC-078 · captured 6:38 ⚠ Pending
L3 slab rebar spacing
Rebar Crew A · L3 slab · 2 photos
QC-072 · captured 6:02 ⚠ Pending
L3 conduit clearance @ B-14
MEP Rough-In · L3 North · 1 photo
QC-070 · due 16:00 ⚠ Pending
L2 fire-stop penetrations Framing Crew B · L2 West · no evidence yet
QC-079 · 6:15 ✕ Failed
Curtain wall anchor torque Curtain Wall Crew · L1 South · punch PL-012 open
QC-074 · 6:20 ✓ Passed
L2 stud spacing verification Framing Crew B · L2 East · 3 photos
✓ Cloud synced 6:41 DR

AI Insights

3 open alerts · model updated 6:30 · Mon, Jul 6

Alert feed

⚠ High rework risk 06:18 · confidence high
3 work packages still reference superseded Rev C3 — anchor torque spec changed in Rev C4 Recommended: republish overlays from Rev C4 to Curtain Wall Crew before the 9:00 lift window.
View affected WPs →
⚠ Sequence deviation 06:32 · confidence medium
MEP Rough-In is ahead of L3 slab pour sign-off (Rev C4) Recommended: hold the L3 conduit run until checkpoint QC-078 is signed off.
Open QC-078 →
ℹ Crew idle pattern this week · confidence high
MEP Rough-In waits on slab sign-offs an average of 40 min/day Recommended: schedule QC sign-offs before the 7:00 crew start to remove the wait.
View idle log →
Rework avoided — last 30 days
$38,400 214 h
From 12 actioned alerts

Error-risk by zone

4%
12%
31% ⚠
18%
7%
3%
L1 L2 L3 L4 L5 L6
⚠ L3 flagged — rebar spacing variance trending up before Wed pour

Material waste trend

6.2% 4.2%
W23 W24 W25 W26 W27
ℹ Rebar offcut waste down 32% since overlay-guided cutting started (W23)
Augvator AI Insights ✓ 6:41

AI Alerts

3 open · model updated 6:30
⚠ High rework risk 06:18
3 work packages still reference superseded Rev C3 — torque spec changed in Rev C4 Republish overlays from Rev C4 to Curtain Wall Crew before 9:00.
⚠ Sequence deviation 06:32
MEP Rough-In is ahead of L3 slab pour sign-off (Rev C4) Hold the L3 conduit run until QC-078 is signed off.
ℹ Crew idle pattern this week
MEP Rough-In waits on slab sign-offs avg 40 min/day Schedule QC sign-offs before the 7:00 crew start.
Charts & analytics: Full analytics on desktop →
✓ Cloud synced 6:41 DR

Devices & Team

12 glasses · 18 team members · Mon, Jul 6
Online 11/12
Low battery ⚠ 2
Firmware 2.4.1 ✓ fleet current
Glasses #03 ⚠ 18%
R. Gagnon · Framing Crew B ✕ Sync failed 22:10
Glasses #12 ⚠ 18%
Unassigned Charging — dock B
Glasses #07 82%
Marc T. · Framing Crew B
✓ Synced 6:41 Overlay: L3 Rebar
Glasses #04 67%
J. Fortin · Rebar Crew A
✓ Synced 6:38 Overlay: L3 Rebar
Glasses #11 91%
K. Tran · Curtain Wall Crew
✓ Synced 6:24 ⚠ Overlay Rev C3
Glasses #01 88%
P. Nair · QC — site-wide
✓ Synced 6:29 Overlay: QC markers
Show all 12 devices →
Augvator Devices & Team ✓ 6:41

Glasses fleet

11/12 online · 2 low battery · firmware 2.4.1
Glasses #03 ✕ Sync failed 22:10
R. Gagnon · Framing Crew B · ⚠ 18%
Glasses #12 ⚠ 18% — charging
Unassigned · dock B
Glasses #07 ✓ Synced 6:41
Marc T. · Framing Crew B · 82% · Overlay: L3 Rebar
Glasses #04 ✓ Synced 6:38
J. Fortin · Rebar Crew A · 67% · Overlay: L3 Rebar
Show all 12 devices →